2021-12-20
Another brand new XDM Ready Mix Concrete Batch Plant model: HZS120, with the capacity of 120m3/hr, just be installed in Chandra, Kaliakoir,Gazipur,Bangladesh in December,2021.
The leading time of this plant (preparation time) is 20days, and the transportation time take another 20 days, and then the installation and commissioning time is about 20 days, so totally it has took 60 days to setup this plant since the date of placing the order.
The whole plant excluding the silos loaded into 4*40HQ containers.